Schedule by Date

Hamilton North of Woodside 01/28/08 06/24/09
Mobilization 01/28/08 02/08/08
Clearing & Grubbing 02/11/08 03/24/08
Muck Excavation 02/11/08 04/25/08
Topsoil 02/11/08 11/21/08
Wetland Topsoil 02/11/08 05/30/08
Special Borrow 02/18/08 10/17/08
Excavation 02/25/08 09/12/08
Bridge 03/17/08 11/05/08
Mobilization 03/17/08 03/20/08
Phase 1 Work 03/24/08 06/16/08
Pile Driving 03/24/08 03/27/08
Beams 03/31/08 04/14/08
Mainline Crossings 04/07/08 08/15/08
Backwalls & Wingwalls 04/15/08 04/18/08
Bridge Deck 04/15/08 06/13/08
Concrete 04/22/08 11/26/08
Hamilton 04/22/08 07/03/08
Prep Sidewalk 04/22/08 05/06/08
Base Gravel 04/28/08 11/21/08
Storm Drain - Hamilton 04/28/08 05/23/08
Sidewalk 05/06/08 06/03/08
Prep Curb 05/26/08 05/28/08
Bridge Barrier Rail 06/02/08 06/04/08
Temporary Shoring 06/02/08 06/06/08
Curb & Gutter 06/03/08 06/10/08
Guard Rail - Phase 1 06/05/08 06/11/08
Groove Deck 06/05/08 06/05/08
Paving - 1st Section 06/09/08 06/30/08
Seal Deck 06/16/08 06/16/08
Phase 2 Work 06/17/08 09/15/08
Remove Timber Bridge 06/17/08 06/23/08
Pile Driving 06/25/08 06/30/08
Beams 07/02/08 07/16/08
Median 07/02/08 07/03/08
Backwalls & Wingwalls 07/17/08 07/22/08
Bridge Deck 07/17/08 09/10/08
Storm Drain - Woodside 07/21/08 08/22/08
Railing 08/28/08 09/03/08
Guardrail - Phase 2 09/04/08 09/10/08
Groove Deck 09/09/08 09/09/08
Seal Deck 09/11/08 09/11/08
Remove Temporary Shoring 09/15/08 09/15/08
Removal of River Bridge 09/15/08 11/05/08
Remove Deck & Trusses 09/15/08 10/07/08
Woodside 09/22/08 11/26/08
Prep Sidewalk 09/22/08 10/03/08
Prep Curb 09/22/08 09/24/08
Curb & Gutter 09/29/08 10/03/08
Sidewalk 10/06/08 10/31/08
Paving - 2nd Section 10/13/08 11/21/08
Install Cofferdam 10/15/08 10/23/08
Remove Piers/Abutments 10/15/08 10/29/08
Remove Cofferdam 11/03/08 11/05/08
Fencing 11/24/08 12/12/08
Median 11/24/08 11/26/08
Seal & Cover 06/12/09 06/19/09
Striping 06/22/09 06/24/09